Reema can complete a piece of work in 12 days while seema can the same work in 18 days. If they both work together, then how many days will be required to finish the work?Select one:
Answers
Answered by
0
one day work of Reema = 1/12
one day work of Seema = 1/18
so , if they work together = 1/12 + 1/18 = 5/36
5/36 - 1 day work
1 - 36/5