Math, asked by kalitaajanta86, 1 day ago

– Regular Rate $16.00/hr
– Overtime Rate $24.00/hr
– Targeted Labour Cost $11,200/wk
– Labour Hours Needed 700/wk
– Any hour worked over 40 hrs/wk must be paid overtime rate

For a 14-person team, how does the actual weekly labour cost compare to the targeted labour cost?

Answers

Answered by akashbodade96112
0

Answer:

labour horse needed 700/wk