Regular Rate $16.00/hr – Overtime Rate $24.00/hr – Targeted Labour Cost $11,200/wk – Labour Hours Needed 700/wk – Any hour worked over 40 hrs/wk must be paid overtime rate

Answers

Answered by kumarikajal111296
0

Given that :

Regular rate : $16/hr

overtime rate : $24/hr

Labour hour needed : 700/wk

overtime : 40hr/week +

Now,

Labour hours needed : 700/wk.

Regular hours : 40 hrs/week

overtime hours : 700-40 = 660 hrs /week

Regular hours price = $16/hr

= 40x16 : $640

Overtime hours price = $24/hr

=24x660 : $15,840

Total Price = $15,840+$640 : $16,480.

Targeted cost = $11,200/wk

Price increase : $16,480 - $11,200

= $5,280. Answer.