Accountancy, asked by umaroy87918, 12 days ago

reorder quantity 12000 unit Lead time for 4 to 8 week maximum consumption 4,000 unit per week, minimum consumption 1550 units per week. re order lavel is??​

Answers

Answered by PappulaHemanth
1

Answer:

32000

Explanation:

rol=max lead time × max consumption