Math, asked by cbc55, 11 months ago

required if
Chailenge
50 workers can complete laying the tiles of a mall in 10 days. How many additional workers are
after 3 days it is decided that the work must be completed in 8 days instead of 10 days?
(d) 5
(b) 10
(C) 20
(a) 40​

Answers

Answered by Sushant05
8

Answer:

It Is C 20.........

Similar questions