Ritu completes a work in 20 days, and Reema completes the same work in 30 days. In how many days they together will complete the same work?​

Answers

Answered by anan500
1

Answer:

12 days

Step-by-step explanation:

20×30÷20+30=600÷50=12 days

Answered by mhendrajangid1977
0

Answer:

12 days

Step-by-step explanation:

20×30÷20+30=600÷50=12days