Math, asked by SaketUpadhyay8199, 9 months ago

rs 780 is paid for a task mohun can do in 6 days , sohun can do in 4 days.if both do together how much money each will recive

Answers

Answered by sahithisidd
0

mohun - 6 days

sohun - 4 days

mohun takes Rs 780 for the task

mohun's 1 st day work - 1/6

sohun's 1 st day work - 1/4

Therefore the ratio of there 1st day work are

1/6:1/4

( take Lcm of the denominator .....

the lcm is 12)

1/6*12:1/4*12

2:3

sum of the ratios is 2 + 3 = 5

mohun's share is 780*6/5 = Rs 936

sohun's share is 780*4/5 = Rs 624