Run out method of scheduling in job is used to,
(a) Determine production runs for a particular product on one machine
(b) Determine production runs for group of jobs that share the same production
facilities.
(c) Determine production, runs for two group of job on two machines
(d) Determine production runs of a single product on two machines.
Answers
Answered by
3
determine production runs for groups of job that share the same production facilities...
Answered by
1
Answer:
Answer is option (b). Determine production runs for group of jobs that share the same production facilities.
Explanation:
Scheduling involves assigning jobs to the employee for a particular period of time. Scheduling techniques help in manufacture process. In run out method scheduling involves in production determination for a group of jobs for one workstation that shares same production facilities. There are few rules for scheduling job at one workstation such as in single dimension rule which is based on the information about the jobs waiting for processing.