Rupesh and Sailesh can do a piece of work in 12 days where as Sailesh
alone can do the work in 16 days. In how many days can Rupesh alone do the
work?
Answers
Answered by
1
Answer:
Rupesh will do the work in 48 days.
Answered by
2
Let sailesh work be A
and
rupesh work be B
(A+B)'s 1 day work = 1/12
"A" first day work = 1/16
"B" first day work = 1/12 - 1/ 16
1/12 * 4/4 - 1/16 * 3/3
4 - 3 /48 = 1/48= 48
Rupesh alone do the work in 48 days