Salim takes 8 days to finish a work . Manoj takes 12 days to finish the same work. Raj works twice as fast as Salim. how many days will all three take to finish the same piece of work?
Answers
Answered by
1
Answer:
24
Step-by-step explanation:
Salim = 8
manoj = 12
raj = 4
together they will complete in 24 days.