Satish is 25% less efficient than Abhishek Bhavya is 100% more efficiant than Satish if Satish Bhavya together can complete the work in 20/3 days find in how many days Bhavya and Abhishek together can complete the work
Answers
Answered by
1
Let days taken by Abhishek to complete work alone be x
So, days taken by Satish to complete work alone = 1.25x
And, days taken by Bhavya to complete work alone = 1.25/2 x = 0.625x
In 1 day, Satish and Bhavya will complete = 1 / 1.25x + 1 / 0.625x
They complete a work in 20/3 days, so
In 1 day they will do 3/20 work
Equating the values we get
1 / 1.25x + 1 / 0.625x = 3/20
1 / 1.25x + 2 / 1.25x = 3/20
3 / 1.25x = 3/20
1.25x = 20
x = 20/1.25
x = 16 days
So, Abhishek completes in 16 days
And, Bhavya completes in 0.625(16) = 10 days
Together they will do in 1 day = 1/16 + 1/10
5/80 + 8/80 = 13/80
Therefore they will together complete the work in 80/13 days.
So, days taken by Satish to complete work alone = 1.25x
And, days taken by Bhavya to complete work alone = 1.25/2 x = 0.625x
In 1 day, Satish and Bhavya will complete = 1 / 1.25x + 1 / 0.625x
They complete a work in 20/3 days, so
In 1 day they will do 3/20 work
Equating the values we get
1 / 1.25x + 1 / 0.625x = 3/20
1 / 1.25x + 2 / 1.25x = 3/20
3 / 1.25x = 3/20
1.25x = 20
x = 20/1.25
x = 16 days
So, Abhishek completes in 16 days
And, Bhavya completes in 0.625(16) = 10 days
Together they will do in 1 day = 1/16 + 1/10
5/80 + 8/80 = 13/80
Therefore they will together complete the work in 80/13 days.