say correctly, i will mark as brainliest
16 men can do 1/2 of a work in 9 days. in how many days will 8men finish the same work?
Answers
Answered by
1
16 men can do 1/2 work in 9 days.
Thus, 16 men can do complete work in 18 days.
No. Of men is inversely proportional to the no. of days required to complete the work.
Let x be the no. of days required to complete the work by 8 men.
Thus,
(16)(18)=8(x)
x=36
Thus, 8 men can finish the work in 36 days.