see the file attached below
Attachments:
Answers
Answered by
1
Answer:
I think it's 3
Step-by-step explanation:
So, if you need 12 workers to complete the job in 60 days, u can write it as 12/60. You can simplify it to 6/30 and then 3/15. 3/15 can be thought as u need 3 workers to complete a job in 15 days. So, adding 3 workers would cut 15 days off of 60 days. hope this helps