Math, asked by jitenrauniyar, 1 year ago

Seema can do a piece of work in 16 days. Reema is found to be 20% less efficient than seema. find in how many days will Reema do the work?

Answers

Answered by TooFree
1

Seema can do the work in 16 days

⇒ 1 day = 1/16 of the work


Find the amount of work Reema can do in a day:

20% of 1/16 = 20/100 x 1/16 = 1/80

Amount of work done in a day = 1/16 - 1/80 = 1/20


Find the number of days Reema needed:

1/20 of the work = 1 day

20/20 of the work = 1 x 20 = 20 days


Answer: Reema needs 10 days