Seven - eight of work is done by 28 men in a week and then leave it. how many men can complete the remaining work

Answers

Answered by pravinsir
0
28 men ------ 7/8 work ------ 7 days

4 men ------ 1/8 work ------ 7 days

28 men ------ 1/8 work ------ 1 day