Math, asked by sadatmrahman2004, 10 months ago

seven men paint a bridge in 15 days. how many days will it take for 3 men ?​

Answers

Answered by tcashu112
6

Answer:

seven men can paint a bridge in 15 days.

one man will paint a bridge in 15×7 days.

three men will paint a bridge in 15×7/3 days

35 days.

Ans: 35 days