Math, asked by tallatdar11, 5 months ago

Seven people need 90 days to repair and paint a heritage building. If the
job should be completed in 15 days, how many more people need to be
employed?

Answers

Answered by Chelseabrandon11
2

Answer:

7 <---> 90  means  7*6 = 42 <---> 15.

42 - 7 = 35.

35 more people need to be employed in addition to 7.

Step-by-step explanation:

Answered by Lewendoski
1

Answer:

2 people is the answer ,,,,,,,,,,,,,