Shabir can finish a work in 18 days and Moin can do the same work in half the time taken by Shabir .working together, how much work will they complete in2 days
Answers
Answered by
5
Answer:
Shabir can finish a work in 18 days
Shabir's one day work = 1/18
Moin can finish the work in 18/2=9 days
Moin's one day work=1/9
(Shabir+Moin)'s one day work = 1/18 + 1/9 = 1/6
In 2 days (Shabir+Moin)'s work = 2×1/6 = 1/3
In 2 days, Shabir n Moin together can finish 1/3rd of the work.