Shahid can do a peice of work in 5 days , Sameer can do the same work in ten days and Salman can do it in 15 days . if All three work together , in how many days can they finish the job?
Answers
Answered by
0
Answer:
We are given that 3 men do the work in 16 days.
So, Work done by 3 men in 1 day =1/16
Now, Work done by 1 man in 1 day = 1/(16∗3)=1/48 days.
Similarly, Work done by 1 woman in 1 day can be found out and it is 1/64
Now, Work done by 12 men in 1 day = 12/48=1/4
Work done by 8 women in 1 day = 8/64=1/8 .
Now, Work done 12 men and 8 women in 1 day = 1/4+1/8=3/8
So, 12 men and 8 men do 3/8 of work in 1 day.
So, to complete the work, it will take them 8/3 days. We Just inverse the fraction found above. This is the beauty of Unitary Method.
So, the total time taken is 8/3 days = 2 Days 16 Hrs
Hope that helps. :)
Step-by-step explanation: