Math, asked by sanjitkumar8, 11 months ago

.Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
A) 42 days
B) 40 days
C) 45days
D) 48day


MaxCloud: Question Is Not Clear... Please Do Write in Urdu (Roman) If You Can.. OR Make it Clear..!!
sanjitkumar8: Que.is clear bro plzz read carefully and reply me. the que. was asked rrb cbt-1 exam.

Answers

Answered by TooFree
33

Answer:

(c) 45 days


Step-by-step explanation:

Define x and y:

Let x be the number of days mayukh takes to complete the work alone.

1 day = 1/x of the work


Let y be the number of days Sharan takes to complete the work alone.

1 day = 1/y of the work


They took 18 days if they work together:

1/x + 1/y = 1/18


Makyukh completed 1/3 of the work:

Number of days needed = 1/3 (x)


Sharan completed the the remaining of the work:

Remaining of the work = 1 - 1/3 = 2/3

Number of days needed = 2/3 (y)


They took 40 days:

1/3 (x) + (2/3) y = 40 days

x + 2y = 120 days


1/x + 1/y = 18 ------------------- [ 1 ]

x + 2y = 120 ------------------- [ 2 ]


From [ 1 ] :

1/x + 1/y = 18

(x + y)/xy = 1/18

18(x + y) = xy

18x + 18y = xy

18y = xy - 18x

18y = x(y - 18)

x = 18y/(y - 18)  ------------ sub into [ 2 ]


18y/(y - 18) + 2y = 120

18y + 2y(y -18) = 120 (y - 18)

18y + 2y² - 36y = 120y - 2160

2y² - 138y + 2160 = 0

y² - 69y + 1080= 0

(y - 24)(y - 45) = 0

y = 24 or y = 45


When y = 24,

x + 2y = 120

x + 2(24) = 120

x = 120 - 48 = 72


When y = 45,

x + 2(45) = 120

x = 120 - 90 = 30


Find the days taken by each of them

Mayukh = 72 days, Sharan = 24 days

Mayukh = 30 days, Sharan = 45 days


Since we know that Mayukh works faster

⇒ Sharan will need 45 days


Answer: (C) 45 days

Answered by 7995984748
18

Answer:

Step-by-step explanation:

Let Mayukh -x, sharan-y Sharan<Mayukh,let 1/3x +2/3y= 40, ...1 given condition , x+y =18.......2 ,. By solving 1 and 2. X=30, 72 y=45, 24. He asked for Sharan ........we take..45days .....because...Mayukh > Sharan efficiency.............so ans 45 days

Similar questions