sheena working alone can embroider a sari in 10days while rihana working alone can complete the same embroidery in 8 days. lf both work together, how long will it take them to finish the embroidery?
Answers
Answered by
4
Answer:
40/9 days taken by both ok
Step-by-step explanation: