Math, asked by karnshivendra6, 12 hours ago

Shikha and Laxmi can do a piece of work in 10 days and 15 days respectively. Both
of them start to work together but Shikha leaves after 4 days.
(i) In how many days would Laxmi finish the remaining work?
(ii) In how many days has the work been finished?​

Answers

Answered by tejasvasingh3
3

Answer:

in six days as I dint know

Answered by ons9898
0

Step-by-step explanation:

LCM of 10 and 15 is 30.

A can do (1/10th) of the work in one day (or 3/30th).

B can do (1/15th) of the work in one day (or 2/30th).

Working together, A and B can do (3/30)+(2/30) = 5/30th of the work in one day. So they would require 30/5 or 6 days to complete the task. Therefore in 3 days A and B together would have done half of the entire work.