Math, asked by manisha010679, 2 months ago

Short answer type questions
If 56 men can do a piece of work in 42 days. How many men will do it in 21 days?​

Answers

Answered by saptarshisaha2007
0

Answer:

112 men

Step-by-step explanation:

no. of men required to do the work in 42 days = 56

no. of men required to do the work in   1 day    = 56 × 42

Therefore,

no. of men required to do the work in   21 days = (56 × 42) / 21

                                                                               = 112 men  