Shusheel and suhas can do a piece of work in 20 days and 30 days respectively. In how many days can they complete the work together?
Answers
Answered by
0
Answer:
Step-by-step explanation:
50 days.
Answered by
0
Answer:
Work done by Susheel = 1/20
Work done by Suhas= 1/30
Work done together= 1/20+1/30
=1/12
No. of days the work can be completed = 12 days