To make 1 m3 of concrete of ratio 1:1.5:3
Dry volume of cement = 1.52 (52% more)
Cement quantity = (1*1.52)/(1+1.5+3) = 0.27 m3
Sand Quantity = 0.27*1.5 = 0.414 m3
Aggregates Quantity = 0.81 m3
1 bag of cement = 50 kg = 0.034 m3
So, Cement in bags for 1 m3 concrete = 0.27/0.034 = 7.94 ~ 8 Bags