shyam takes 9 days more than Ram to complete a work .Together they can do the work in 6 days.How many days will shyam take to do that work alone
Answers
Answered by
14
Step-by-step explanation:
let the work done by ram be 'x'
let the work done by shyam be 'y'
according to the question
time taken by shyam = time taken by ram + 9 days
y= x+ 9 ............1
wok done by ram + work done by shyam = 6 days
.............2
now,
wok done by them in one day
:- 1/ x + 1/y = 1/6
we know that
y= x+9 ( from ......1)
so ,
1/ x + 1/ x+9 =1/6
here after taking lcm
x+ x+9 / x^2+9x= 1/6
6(2x+ 9) = x^2+9x
12x + 54 = x^2+9x
equation :-
x^2 - 3x - 54 = 0
solving it by factorisation
x^2 - 9x+6x-54 =0
x( x-9) +6( x-9) =0
( x+6)(x-9)= 0
taking :
x+6=0 x-9=0
x = -6 x =9 days
mot possible
y= x+9
y=18days