Math, asked by SohamKushe, 4 months ago

Shyam took 14 days to finish 70% of the work allotted to him. Due to a shortage of time, he takes help from one of his friends Krishna and together they took 2 days to finish
the remaining work. How long would have Krishna taken
to finish the entire work working alone?​

Answers

Answered by meeraodaka
1

Answer:

ok I will try to answer your questions

Answered by Tridev4
0

Answer:

10 days

Step-by-step explanation:

Let total work be 100, then Shyam did 70 (units) work in 14 days

⇒Shyam does 70/14= 5 work in a day

Now, 30/2=(5+Krishna's work rate)

⇒Krishna does 10 work in a day

So, Krishna will take 10 days to do 100 work