Math, asked by menezes1227, 10 months ago

sita can do a piece of work in 3days Rita can do it alone in 6days and Gita in 9days if all three work together in how many days can they complete the work

Answers

Answered by Anonymous
1

Answer:

Work done by Sita in 1 day = 1/3 of the total work

Work done by Rita in 1 day = 1/6 of the total work

Work done by Gita in 1 day = 1/9 of the total work

If they work together, the work done by them in one day would get combined.

Work done by all of them in 1 day = 1/3 + 1/6 + 1/9

                                                        = 6 + 3 + 2/18

                                                        = 11/18

Work done by all of them in 2nd day = 2 x 11/18 = 22/18

22/18 is greater than total work, which is 1.

Therefore, they all can do the work in 2 days

Answered by parveenansari1909
0

2 day

Step-by-step explanation:

11/18 is your answer