Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?
Answers
Answered by
2
Answered by
8
The number of days needed is inversely proportion to the number of machines needed.
⇒ The more days we have, the fewer machines we need
⇒ The fewer days we have, the more machines we need
16 machines can finish the job in 12 days:
⇒ 12 days = 6 machines
⇒ 1 day = 12 x 6 = 72 machines
Find the number of machines needed if we have 8 days:
⇒ 1 day = 72 machines
⇒ 8 days = 72 ÷ 8 = 9 machines
Number of additional machines needed:
Addition machines needed = 9 - 6 = 3
Answer: 3 additional machines are needed to finish the work in 8 days
Similar questions