Math, asked by skybluedolly, 10 months ago


six men can complete a work in 12 days.2 days later,6 more men joined.how many days will they take to complete the remaining works?

Answers

Answered by sneha9305
1

Step-by-step explanation:

On which topic this question is based on please tell me fast

Answered by kingofself
0

Answer:  

7 days will take to complete the remaining works.

Solution:

According to the question:

Given Data:

Number of men worked = 6 men

Number of days men worked=12 days

To Find:

Calculate how many days they will take to complete the remaining works

Step-by-step explanation

Step 1:

6 men can complete a job in = 12 days.  

6 men work in 12 days =   6\times12   = 72 days

Step 2:

2  days the work   is 6 \times2   = 12 days of work.  

Step 3:

Remaining work to be done   = 72 – 12   = 60 days of work.  

Step 4:

Thus if 6 more men are added, then the work force becomes 12 men strong.

Step 5:

Hence, the remaining work can be completed in -   \frac{60}{12}=5

= 5 man days

Step 6:

Result:

The Final answer is 7 days.