six men can complete a work in 12 days . two days later , 6 more men joined them .How manydays will they take to complete the reamining work
Answers
Answered by
1
Answer:
it will take 4 days
Step-by-step explanation:
if it takes 12 days for 6 men it would take 6 days for 12 men but 2 days are already gone so it will be 4 days