Six people can dig a trench in 8 hours. (a) How long would it take 12 people? (b) How many people would it take to dig the trench in 3 hours?
Answers
Answered by
1
Answer:A- 4HRS(ANS)
B- 16 PEOPLE(ANS)
Step-by-step explanation: