Six women, working eight hours per day, can complete a sewing assignment in five days. How long will the assignment take four women, working at the same rate for 5 hours per day?

Answers

Answered by ManavSenguptaDPS
1
6 women working 8hrs can complete a sewing assignment in=5 days
1 women working 8hrs can complete a sewing assignment in=5*6 days
1 women working 1hr can complete a sewing assignment in=(5 *6*8)days
4 women working 1hr can complete a sewing assignment in=(5*6*8)/4 days
4 women working 5hrs can complete a sewing assignment in=(5*6*8)/4*5 days
=12 days
Hope I have helped You!