Sixty men can build a wall in
40 days, but though they begin the work together, 5 men quit every ten days. The time needed to build the wall is:
Answers
Answer:
Answer
60 men can build a wall in 40 days
Fraction of work done by 1 men in 1 day =1/(60*40) = 1/2400
In 1st 10 days fraction of work done
= 1/2400*10*60 = 1/4 =12/48
Next 10 days fraction of work done
= 1/2400*10*55 = 11/48
Next 10 days fraction of work done
= 1/2400*10*50 = 5/24 =10/48
Next 10 days fraction of work done
= 1/2400*10*45 = 3/16 =9/48
In 40 days fraction of work done
= (12+11+10+9)/48 = 42/48
Remaining fraction of work = 6/48 = 1/8
if x is the no of days to complete 1/8 work with 40 men, then
1/2400*x*40 = 1/8
x = 15/2
total no of days required = 10+10+10+10+15/2
=47 1/2days
Step-by-step explanation:
Hope it will help
Total man days = 2400
60 × 10 × 55 × 10 + 50 × 10 + 45 × 10
= 2100
man days
300/40 = 7.5 days
Total days
= 10 + 10 + 10 + 10 + 7.5 = 47.5 days.