Sixty men can stitch 150 shirts in 30 days working 8 hours a day. In how many days can 35 men stitch 200 shirts working 6 hours a day ?
A) 87.5
B) 89
C) 91.5
D) 93.5
Answers
Answered by
1
Answer:91.5
Step-by-step explanation:
Answered by
0
"D2 = (60 x 30 x 8 x 200) / (150 x 35 x 6) => D2 = 91.42 days =~ 91.5 days.
"HOPE IT HELPS
"PLEASE MARK ME BRAINLIEST ☺️