Smith and Johnson together can do a piece of work in 4 days.
If they had to work separately, the time taken by Johnson to do
the work would be more than that of Smith by 6 days. In how
many days can Smith alone do the work?
please answer it
no spam
wrong answers will get report
Answers
Answered by
0
Answer:
A=Smith B =Johnson
Step-by-step explanation:
(A+B)'s 1 day's work =
4
1
A's 1 day's work =
12
1
B's 1 day's work =(
4
1
−
12
1
)=
6
1
Hence, B alone can complete the work in 6 days