Math, asked by maanavguptaa, 11 months ago

solve in detail plz......

Attachments:

Answers

Answered by Anonymous
2
work done by A in 1 day = 1/12

work done by B in 1 day = 1/15

work done by C in 1 day = 1/20

work done by A+B+C in 1 day = 1/12 + 1/15 + 1/20
= 5+4+3)/60

= 12/60
= 1/5

1/5 th work done in 1 day

So total work done in 5 days