GIVEN :-
- A ᴀʟᴏɴᴇ ᴄᴀɴ ᴅᴏ ᴀ ᴡᴏʀᴋ ɪɴ 4 ᴅᴀʏs .
- B ᴀʟᴏɴᴇ ᴄᴀɴ ᴅᴏ ᴀ ᴡᴏʀᴋ ɪɴ 6 ᴅᴀʏs .
TO FIND :-
- Tʜᴇ ᴛɪᴍᴇ ᴛʜᴇʏ ᴡᴏᴜʟᴅ ᴛᴀᴋᴇ ɪғ ᴛʜᴇʏ ᴡᴏʀᴋ ᴛᴏɢᴇᴛʜᴇʀ .
SOLUTION :-
ʟᴇᴛ,
Tʜᴇ ᴛᴏᴛᴀʟ ᴡᴏʀᴋ = 1
Fᴏʀ 'A' :-
➪ A ᴄᴀɴ ᴀʟᴏɴᴇ ᴅᴏ ᴛʜᴇ 1 ᴡᴏʀᴋ ɪɴ 4 ᴅᴀʏs .
☯︎ Sᴏ, ɪɴ ᴏɴᴇ ᴅᴀʏ A ᴄᴀɴ ᴅᴏ = ᴡᴏʀᴋ .
Fᴏʀ 'B' :-
➪ B ᴄᴀɴ ᴀʟᴏɴᴇ ᴅᴏ ᴛʜᴇ 1 ᴡᴏʀᴋ ɪɴ 6 ᴅᴀʏs .
☯︎ Sᴏ, ɪɴ ᴏɴᴇ ᴅᴀʏ B ᴄᴀɴ ᴅᴏ = ᴡᴏʀᴋ .
Fᴏʀ ʙᴏᴛʜ 'A' ᴀɴᴅ 'B' :-
➪ ʟᴇᴛ, A ᴀɴᴅ B ᴛᴏɢᴇᴛʜᴇʀ ᴅᴏ ᴛʜᴇ 1 ᴡᴏʀᴋ ɪɴ X ᴅᴀʏs .
☯︎ Sᴏ, ɪɴ ᴏɴᴇ ᴅᴀʏ A ᴀɴᴅ B ᴄᴀɴ ᴅᴏ = ᴡᴏʀᴋ .
- ➳ X = 12/5 = 2.4 Days .
Tʜᴇ ᴛɪᴍᴇ ᴛʜᴀᴛ ʙᴏᴛʜ A ᴀɴᴅ B ᴡᴏᴜʟᴅ ᴛᴀᴋᴇ ɪғ ᴛʜᴇʏ ᴡᴏʀᴋ ᴛᴏɢᴇᴛʜᴇʀ ɪs "2.4 ᴅᴀʏs" .
____________________________________________________________
Answered by
0
Answer:
the answer is 2.4 days
Step-by-step explanation:
In 4 days A can do 1 work
In 1 day A can do 1/4 work
Again,
In 6 days B can do 1 work
In 1 day B can do 1/6 work
then,In 1 day A and B can do (1/4+1/6)work
=10/24work
10/24 work done by A and B in 1 day
1 work done by A and B in {1/(10/24)}days
=24/10days
=2.4 days