Math, asked by ali130107, 4 months ago

Solve this Problem fast...​

Attachments:

Answers

Answered by netragupta9
1
Answer:
6 days

Explaination:
A finishes the work in 16 days. A finishes 1/16 of the work in one day. in 1 day B finishes 1/12 of the work. A and B together can complete the remaining work= (7/8) / (7/48)= 7*48/8*7 = 6 days.