Solve this puzzle..
Person A work complete in 20 days.. Person B work complete work in 30 days. If persons A , B, &C together work completed in 7 days. Total work value Rs 6000/-. Then what share will get to Person C?
Answers
Answered by
28
Gɪᴠᴇɴ :-
- A complete work in = 20 days.
- B complete work in = 30 Days.
- (A + B + C) complete work in = 7 Days.
- Total work value = Rs.6000 .
Tᴏ Fɪɴᴅ :-
- share of C ?
ᴄᴏɴᴄᴇᴘᴛ ᴜsᴇᴅ :-
- The money Paid is In the ratio of Their Efficiency when they do same work together ...
Sᴏʟᴜᴛɪᴏɴ :-
LCM of (20,30,7) = 420 units = Let Total work done.
Than,
→ Efficiency of A = (Total work) / (Total No. of Days). = (420/20) = 21 unit/Day.
→ Efficiency of B = (Total work) / (Total No. of Days). = (420/30) = 14 unit/Day.
→ Efficiency of (A+B+C) = (Total work) / (Total No. of Days). = (420/7) = 60 unit/Day.
So,
→ Efficiency of C = (A + B + C) - A - B = 60 - 14 - 21 = 25 unit/day.
Therefore,
→ share of A : B : C = 21 : 14 : 25
And,
→ share of C = (25/60) * 6000 = Rs.2500 (Ans.)
Hence, Rs.2500 share will get to Person C..