solve this question
Attachments:
Answers
Answered by
1
Answer:
X1= no. of men were before(12)
X2= no. of men present(16)
Y1= time that would have taken to complete the work by 12 men(12)
Y2= time required to complete the work by 16 men(x)
X1Y1=X2Y2
12×18=16x
(12×12)÷16=x
9=x