Total work =12x8=96 units
Work completed in 3 day =12x3=36units
Work left =60
Time =4day
Men power required=60/4=15
=15-12
=3men
This is ur ans hope it will help you in case of any doubt comment below
Work completed in 3 day =12x3=36units
Work left =60
Time =4day
Men power required=60/4=15
=15-12
=3men
This is ur ans hope it will help you in case of any doubt comment below