Math, asked by Jenniliya77, 1 month ago

Solve this question of Direct and Inverse variation.

A can make a wooden cupboard alone in 15 days, while B alone can complete in 12 days. They worked together for 3 days and then B leaves. In how many days will A finish the remaining work.

Answers

Answered by mayajakhar79
4

Solution:-

━━━━━━━━━━━━━━━━━━━━━━━━━━

ANSWER:-

  • A will complete the work in \tt{8\dfrac{1}{4}} days after B leaves.

GIVEN:-

  • Time taken by A to complete a wooden cupboard = 15 days
  • Time taken by B to complete a wooden cupboard = 12 days
  • Time they worked together = 3 days

TO FIND:-

  • In how many days will A finish the remaining work = ?

SOLVING STEP BY STEP:-

  • Work done by A in a day = 1/15
  • Work done by B in a day = 1/12
  • Sum of the work both do in a day = 1/15 + 1/12
  • (1/15) + (1/12)
  • LCM of 15 and 12 is 60.
  • (4 + 5)/60
  • (4 + 5)/60 = 9/60
  • So, A and B together do 9/60 of the total work in a day.
  • Sum of the work both do in 3 days = (9/60) × 3
  • (9/60) × 3
  • Cancel 60 by 3.
  • 9/20
  • So, A and B together do 9/20 of the total work in 3 days.
  • After that B left:-
  • Work remains = (1 - 9)/20
  • LCM is 20
  • (20 - 9)/20
  • (20 - 9)/20 = 11/20
  • Work remains is 11/20 of the whole work.
  • A alone will finish the work in days = (11/20) × 15
  • (11/20) × 15
  • Cancel 20 and 15
  • (11/4) × 3
  • (11/4) × 3 = 33/4
  • 33/4 = \tt{8\dfrac{1}{4}}
  • \tt{8\dfrac{1}{4}} days.
  • So, A will complete the work in \tt{8\dfrac{1}{4}} days after B leaves.

━━━━━━━━━━━━━━━━━━━━━━━━━━

Similar questions