A and B can do a work in 8days, B and C in 12days, and A and C in 16days. In what time can they do it, all working together
Answer with Explanation(only condition for brainliest)
Answers
Answered by
0
Answer:
Hey mate nice que
Ans:- Hey mate from my opinion
ans
C+B=12
A+B=8
-. -. -
= C-A=4
C=4+A
putting these value in eqn
A+C=16
A+4+A=16
A=6
B=2
C=10