Some carpenters promised to do a job in 9days but 5 of them were absent and remaining did the job in 12 days. What was the original number of carpenters?
Answers
Answered by
0
Answer:
20
Step-by-step explanation:
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
A) 24
B) 20
C) 16
D) 18
Correct Answer:
B) 20