Some men promised to do a job in 40 days. 12 of them were absent and the remaining men did the job in 60 days. What is the original number of men?
Answers
Answered by
0
Let there be m men in the beginning, who promised to do the job in 40 days.
But 12 became absent, means the remaining (m – 12) men did the job in 60 days.
The work is same ⇒40m = 60(m – 12) ⇒40m = 60m - 720 ⇒ m = 36.Hence, answer is 36 men.
Answered by
5
Answer:
hiiiiii
your answer is here !
Step-by-step explanation:
Let there be m men in the beginning,
who promised to do the job in 40 days.
But 12 became absent,
means the remaining (m – 12) men did the job in 60 days.
The work is same
⇒40m = 60(m – 12)
⇒40m = 60m - 720
⇒ m = 36.
Hence, answer is 36 men.