sonal and Preeti started working on a project and they can complete the project in thirty days. sonal worked for 16 days and Preeti completed the remaining work in 44 days. how many days would Preeti have taken to complete the entire project all by herself?
Answers
Answered by
5
Answer:
Hi,
╔════════════════════════════════════════════╗
-Puja works for 16 days. Preeti works for 44 days.-
-So we can consider puja and Preeti working together for 16 days and Preeti works alone for (44–16)= 28 days.-
-So 16/30= 8/15 part of the work is done by them.-
-The remaining (1–8/15)= 7/15 part of the work is done by Preeti on 28- days.-
-So Preeti alone can complete the whole work in = 28x (15/7) = 60 days.-
╚════════════════════════════════════════════╝
Please mark as brainliest
Answered by
0
Answer:
Step-by-step explanation:
question is incorrect as preeti completed whole work in 44 days .not the remaining work.hence answer is 60