Math, asked by Hasanat4884, 3 months ago

sonia and mohit can together do work in 20 hours . if mohit alone can do work in 30 hours , if long will it take for sonai to do it alone ?

Answers

Answered by Sagniki
0

Step-by-step explanation:

1

Sameer can finish a work in 20 days Mohit can finish the same work in 24 days and Binesh can finish the same work in 36 days. Sammer first works for 5 days and leave. How many days will Mohit and Binesh need to finish the remaining work?

Neil Gordon

Answered 14 November 2019

Semeer x 20 days completes the work =:100% performance one days work is 5 %

Mohit can finsh the same amount of work in 24 days = 80% efficience perfomance

Binesh can finish the same amount of work in 36 days = 64 % efficiency performance,ģ

Sammer? Spelling mistake first works for 5 days , Therefore before he left job was 25 % complete. And 75 % of the work is outstanding is 75% remains

So Mocit & Binesh are to complete the remainig 75 % work content, based on Ssmeers performancr

Mohit 3/4 of 24 days = 18 days 18÷ 3 = 6 ( 6 days or 25 % carried out by Smeer)

Binesh 3/4: of 36 days = 27 days 27÷ 3 = 9 ( 9 days or 25% carried out by Smeer)

Answer = 15 days working together = combined work efficiency 80% & 64 % = 144% of Semeers 100%

15 days at 100 = 1500 / 10.3 days × 144 = 1500

Mohit 80 % and Binesh 64% working together is combined performance of144 %

require 10.3 days instead of Sameer 15 days at 100 %

Similar questions