Math, asked by talhaasif485, 10 months ago

Sonichi Electronics manufactures small electronic consumer items such as portable clocks, calculators, and radios. The company is concerned about the high cost of its product-inspection operation. As a result, it had its industrial engineering department conduct a time study of an inspector who inspects portable radios. The operation consists of seven elements, as follows: (1) The package is opened and the radio is removed; (2) the battery casing cover is removed; (3) two AA batteries are inserted; (4) the radio is turned on, and the inspector tunes to a station and listens briefly to at least two stations; (5) the radio is turned off and the batteries are removed; (6) the battery cover is replaced; and (7) the radio is repackaged. The time-study observations (in minutes) for 10 cycles are shown in the following table.


a. The allowance factor for this job is 15%. Determine the standard time.


b. If management wants the estimate of the average cycle time to be within 0.03 minute with a 95% level of confidence, how many job cycles should be observed?



c. Management is considering putting inspectors on a piece-rate wage system in order to provide them with greater incentive to inspect more items. What effect might this have on the quality-inspection function?

Attachments:

Answers

Answered by adityakarodiwal
0

Answer:

Sonichi Electronics manufactures small electronic consumer items such as portable clocks, calculators, and radios. The company is concerned about the high cost of its product-inspection operation. As a result, it had its industrial engineering department conduct a time study of an inspector who inspects portable radios. The operation consists of seven elements, as follows: (1) The package is opened and the radio is removed; (2) the battery casing cover is removed; (3) two AA batteries are inserted; (4) the radio is turned on, and the inspector tunes to a station and listens briefly to at least two stations; (5) the radio is turned off and the batteries are removed; (6) the battery cover is replaced; and (7) the radio is repackaged. The time-study observations (in minutes) for 10 cycles are shown in the following table.

a. The allowance factor for this job is 15%. Determine the standard time.

b. If management wants the estimate of the average cycle time to be within 0.03 minute with a 95% level of confidence, how many job cycles should be observed?

c. Management is considering putting inspectors on a piece-rate wage system in order to provide them with greater incentive to inspect more items. What effect might this have on the quality-inspection function?