soumya takes 6 days less than number of days by bhagya to complete a piece of work. if both together can complete same work in 4 days how many days will bhagya alone complete the work
Answers
Answered by
10
thanks for asking the question
Attachments:
kaifulla23:
y we have to take the reciprocal
Answered by
7
Answer:
Bhagya alone complete the work in 12 days.
Step-by-step explanation:
Let x be the no of days taken by Soumya and y be the no of days taken by Bhagya.
according to the question,
x = y - 6 ............... (1)
............(2)
Value of x from (1), put in (2)
we get,
⇒ y = 2 & 12
when y = 2 we get x = 2 - 6 = -4 which is not possible
when y = 12 we get x = 12 - 6 = 6
Therefore, Bhagya alone complete the work in 12 days.